Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedNueva Aldea Biomass Power Plant Phase 1 (0258)
DOE that requested for issuance and date of requestSGS (04 Mar 09)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
Further clarification is required on:
1.1) How the DOE verified the measurement of the volume of the biomass entering the plant.
1.2) How the DOE cross-checked the biomass measurements against an annual energy balance based on purchased quantities and stock changes as per the methodology.
2. How the DOE verified that the choice of using simple adjusted Operating Margin (OM) is in accordance with the applied methodology ACM0002, which specifies dispatch data analysis as the first methodological choice for OM calculation.
3. The appropriateness of calculating CERs for the year 2008 using grid emission factor calculated based on only nine months data for the year of 2008.
Date 04 Apr 09