07:08 01 Jul 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | 3.5 MW Rice Husk based Cogeneration Project at Oswal Woolen Mills Ltd. (0118) |
---|---|
DOE that requested for issuance and date of request | DNV (15 Jun 09) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The PP/DOE shall further clarify the following issues: 1) Why there was electricity generation on the 20th January 2008, while during the period from 21:45 18 January 2008 to 04:27 21 February 2008 the plant was shut down (p.4 of monitoring report). And the plant was shut down from 04:05 on 14 July 2008 to 05:05 on 15 July 2008 but the power generation on 14 July reached over 90% of the daily average in the month. 2) Why there were no meter reading changes on the date (11 June 2008) when the calibration for all the meters (generation meter, auxiliary meter, and net electricity export meter) took place. OTHER ISSUE(S) 3) The number of total outage hours is inconsistent between the verification report (p.6, 1033 hours 9 minutes) and the monitoring report (p.4, 1021 hours 9 minutes). Clarification is required. |
|
Date | 21 Aug 09 |