Project title of the project activity or programme of activities (PoA) for which issuance is requestedTétouan Wind Farm Project for Lafarge Cement Plant (0042)
DOE that requested for issuance and date of requestDNV (06 Jan 10)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
1. The DOE shall clarify how it confirmed that the guidelines for small scale project activities which require recalibration of meters at least once in three years was complied with considering that after the initial calibration of the meters on 04th January 2005 the recalibration was conducted on 22nd December 2008.
2. The DOE shall further clarify the reason for discrepancy in the accuracy class of the meter used as it mentioned the accuracy class as 0.5S but it also mentioned in the verification report that the calibration records refer the accuracy class of meters as 0.2S.
Date 31 Mar 10