12:33 15 Jan 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Salvador da Bahia Landfill Gas Management Project (0052) |
---|---|
DOE that requested for issuance and date of request | EPIC (16 Dec 21) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
1) The DOE is requested to further elaborate how it determined that the efficiency of the gas engine of 38.5%, applied in the request for deviation to determine the methane destroyed in the power plant, ensures that the calculations of GHG emission reductions are conservative considering that: the value applied is in the lower bound value of the range of efficiencies observed for other comparable commercial LFG engine-generator sets, i.e. between 38.1% and 44%; no cross-check was made with the efficiency of engines calculated after the 19 flow-meters were installed on 25/03/2013. Please refer to Paragrah 283 of the VVS-PA version 3.0.. |
|
Date | 07 Jul 22 |