01:46 31 Jan 25
Project:
7507 Qinghai Maqin Gequ Level 2 Hydropower Station
- Issuance Request
Project | 7507: Qinghai Maqin Gequ Level 2 Hydropower Station |
---|---|
ISSUANCE STATUS | Issued (on 11 Jan 22) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Oct 15 - 31 Dec 20 |
Monitoring report | Monitoring report (233 KB) |
Request for issuance | Signed form (64 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
1,106,875
Serial Range:
Block start: CN-5-1127675869-2-2-0-7507
Block end: CN-5-1128782743-2-2-0-7507
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (242 KB) Verification report (242 KB) |
Additional documents |
MR-Gequ-2021.pdf (266 KB)
Untitled (uploaded 20 Sep 21 18:42:09) (57 KB) |
Offset now: visit the United Nations Carbon Offset Platform