02:19 27 Feb 26
Project:
7308 Fugu County Yabo 30MW Semi-coke Waste Gas Power Generation Project
- Issuance Request
| Project | 7308: Fugu County Yabo 30MW Semi-coke Waste Gas Power Generation Project |
|---|---|
| ISSUANCE STATUS | Issued (on 14 Oct 16) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 13 - 31 Mar 16 |
| Monitoring report |
Monitoring report (837 KB)
|
| Request for issuance |
Signed form (235 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
391,389
Serial Range:
Block start: CN-5-995425770-2-2-0-7308
Block end: CN-5-995817158-2-2-0-7308
|
| Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (591 KB)
Verification report (591 KB)
|
| Additional documents |
Yabo 2nd MR V02_cl.pdf (861 KB)
Yabo 2nd monitoring period version 01.xls (48 KB)
|

Monitoring report
Yabo 2nd monitoring period version 01.xls
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: