07:04 23 Feb 25
Project:
4317 Ningxia Taiyangshan Wind Farm Second Phase 49.5MW Project
- Issuance Request
Project | 4317: Ningxia Taiyangshan Wind Farm Second Phase 49.5MW Project |
---|---|
ISSUANCE STATUS | Issued (on 09 Mar 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 24 Jan 11 - 31 Aug 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
57,706
Serial Range:
Block start: CN-5-527518870-1-1-0-4317
Block end: CN-5-527576575-1-1-0-4317
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: