22:49 09 Jul 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 9613 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Power Generation using Waste pressure Energy of BF gas from Gas Expansion Turbine Station of BF-3 of Rashtriya Ispat Nigam Limited |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) 1.The DOE is requested to clarify how the input parameter “ Escalation in O&M cost” is applicable at the time of investment decision since the value for this parameter is sourced from CERC Tariff Order dated January 2009 whereas the investment decision is in May 2006. 2.The DOE shall also clarify why the savings from the avoided Contract Maximum Demand (CMD) charges due to the operation of 14MW project activity is not taken into account in the IRR calculation. In doing so, the DOE shall validate the impact on IRR after inclusion of CMD charges. Please refer to para 6 of EB 62 Annex 5, VVS version 05 Para 120 (d). 2) 3.The DOE/PP is requested to state the different power source to meet the increased demand (102 MW) of the facility after the project implementation. In doing so please provide the installed power generation capacity from each fuel source: existing coal based CPP, greenfield coal based CPP (please state if already commissioned, and when), grid power import and the 14 MW under the Project activity . 4.The DOE is requested to clarify how it validated that grid is the the most plausible and credible baseline scenario given the fact that : i)The baseline alternatives donot have comparable level of service/outputs in terms of power generation (for instance Option P7 and P9 refers to alternative scenarios for 14 MW , Option P8 (greenfield fossil fuel plant) refers to alternative for 119MW, Option P10 (grid) refers to 35 MW). ii) The DOE is also requested to provide the investment comparison analysis from all the credible alternatives to meet the increased power demand after capacity expansion of the facility as required by Step 2 Option 2 of Baseline Determination section of the applied methodology ACM0012 ver 4. iii)The DOE is required to validate whether all possible baseline alternatives have been included such as,(a) installation of a Greenfield 100 MW Coal based Captive Power Plant (b) installation of l turbine of 32 MW capacity in addition to the 67.5MW turbine in the greenfield coal based captive power plant which will cater to the increased power demand . iii) The DOE is requested to clarify the different power generation based on waste gas /heat/pressure that is existing in the facility of RINL, in particular ,the DOE is requested to clarify how it validated Options P7 and P9 of the PDD and correct the inconsistencies between them. Please refer to VVS version 05 para 89-93; Step 2- Option 2 of ACM0012 ver 4. |
|
Date | 25 Mar 14 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: