22:43 04 Nov 25
Project:
9003 LMEL 25 MW Waste Heat based Captive Power Plant.
- Issuance Request
| Project | 9003: LMEL 25 MW Waste Heat based Captive Power Plant. |
|---|---|
| ISSUANCE STATUS | Issued (on 10 Mar 17) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jul 14 - 30 Jun 16 |
| Monitoring report | Monitoring report (541 KB) |
| Request for issuance |
Signed form (249 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
124,769
Serial Range:
Block start: IN-5-226630067-2-2-0-9003
Block end: IN-5-226754835-2-2-0-9003
|
| Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (669 KB)
Verification report (669 KB)
|
| Additional documents |
MR LMEL (746 KB)
Summary sheet 01 (60 KB) Summary sheet 02 (70 KB) Electrical (5552 KB) Production (5262 KB) |

Signed form
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: