17:46 08 Dec 25
Project:
8761 Stung Tatay Hydroelectric Project
- Issuance Request
| Project | 8761: Stung Tatay Hydroelectric Project |
|---|---|
| ISSUANCE STATUS | Issued (on 03 Aug 17) completeness check: complete | info & rep check: concluded |
| Monitoring period | 28 Dec 15 - 27 Dec 16 |
| Monitoring report |
Monitoring report (489 KB)
|
| Request for issuance |
Signed form (156 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
563,407
Serial Range:
Block start: KH-5-638734-2-2-0-8761
Block end: KH-5-1202140-2-2-0-8761
|
| Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (881 KB)
Verification report (881 KB)
|
| Additional documents |
ER calculation spreadsheet_Stung Tatay_2nd (82 KB)
MR(V02)_Stung Tatay_2nd (431 KB)
|

Monitoring report
ER calculation spreadsheet_Stung Tatay_2nd
Offset now: visit the United Nations Carbon Offset Platform