Project:
6909 Grid connected solar PV power plant in Jodhpur, Rajasthan
- Issuance Request
Project | 6909: Grid connected solar PV power plant in Jodhpur, Rajasthan |
---|---|
ISSUANCE STATUS | Issued (on 10 Nov 22) completeness check: complete | info & rep check: concluded |
Monitoring period | 14 Sep 12 - 13 Sep 19 |
Monitoring report | Monitoring report (368 KB) |
Submission of comments to the DOE | |
Request for issuance | Signed form (249 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
2,850
CERs issued from 01 Jan 2013 until 31 December 2020: 56,699 Total amount of CERs: 59,549
Serial Range:
Block start: IN-5-304836677-2-2-0-6909
Block end: IN-5-304893375-2-2-0-6909
Serial Range: Block start: IN-5-304893376-1-1-0-6909 Block end: IN-5-304896225-1-1-0-6909 |
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
Certification report (854 KB) Verification report (854 KB) |
Additional documents |
MR UN 6909 TQC 35121 (585 KB)
ER UN 6909 TQC 35121 (42 KB) |
Offset now: visit the United Nations Carbon Offset Platform