6870 Grid connected solar PV power plant in Kutchh district of Gujarat
- Issuance Request
| Project | 6870: Grid connected solar PV power plant in Kutchh district of Gujarat |
|---|---|
| ISSUANCE STATUS | Issued (on 06 Feb 23) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Apr 14 - 31 Jul 19 |
| Monitoring report |
Monitoring report (757 KB)
|
| Request for issuance |
Signed form (190 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
40,781
Serial Range:
Block start: IN-5-315212549-2-2-0-6870
Block end: IN-5-315253329-2-2-0-6870
|
| Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
Certification report (254 KB)
Verification report (254 KB)
|
| Additional documents |
Untitled (uploaded 28 Oct 22 14:12:01) (29 KB)
Untitled (uploaded 28 Oct 22 14:12:02) (913 KB)
|