20:23 10 Feb 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 5366 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Refurbishment of Enguri Hydro Power Plant, Georgia |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) The DOE is requested to clarify how it validated the start date of the project activity as 21/12/2005, considering that; a) normal rehabilitation work resumed at the project site within 5 weeks of a preliminary notice of termination being sent by the contractor to the project participant (PP), which indicates that project implementation never ceased on the ground. The DOE may also justify how it validated the statement in the validation report (page 17) that project work had already ceased owing to severe financial problems faced by the project activity for over 24 months. b) the Board resolution dated 21/12/2005 only considered CDM benefits for units 1 and 2 (PDD page 30), and not units 4 and 5 In doing so, the DOE may refer to the definition of start date as clarified by the Board in EB 41 for project activities that are restarted due to consideration of the benefits of the CDM, the cessation of project implementation must be demonstrated by means of credible evidence such as cancellation of contracts or revocation of government permits. Please refer to VVM paragraph 104 (a). 2) The DOE is requested to clarify how it validated prior consideration of CDM for units 2 and 4 considering that the PP obtained a loan for the rehabilitation of these units in December 2001, signed a contract with VSH in November 2002, and without any real termination of the contract, project works continued at the site and were completed by August 2009 for both the units. The DOE is requested to clarify how it validated prior consideration of CDM for unit 5 considering that the Board resolution dated 21/12/2005 does not include CDM consideration to proceed with rehabilitation of unit 5, but only units 1 and 2 (PDD page 30). Please refer to VVM paragraph 104 (b). 3) The DOE is requested to further substantiate how it validated the investement barrier - lack of private capital, considering that the PP had access to both national loan (USD 200,000 from Georgian Procredit Bank) and international loans (approximately USD 30 million from EBRD) as sources of finance for the project activity. In doing so, please refer to the 'Combined tool to identify the baseline scenario and demonstrate additionality', sub-step 2a. Investment barriers, page 7. (EB 60, Annex 7). The DOE is requested to further substantiate how it validated the investment barrier - risks due to level of tariffs, considering that the generation tariff was reduced in June 2006 from 2.13tetri/kWh to 1.187tetri/kWh, which is after the date of investment decision (21/12/2005). Please refer to VVM paragraph 118 (a), (b). |
|
Date | 03 Jan 12 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: