14:21 22 Mar 23
Project:
4146 Inner Mongolia Zhalute Arikunduleng Wind Farm Project
- Issuance Request
Project | 4146: Inner Mongolia Zhalute Arikunduleng Wind Farm Project |
---|---|
ISSUANCE STATUS | Issued (on 08 Mar 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 10 Feb 11 - 30 Jun 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
98,664
Serial Range:
Block start: CN-5-754015516-1-1-0-4146
Block end: CN-5-754114179-1-1-0-4146
|
Verification and certification reports |
VVS/VVM version:
VVS 2.0
![]() ![]() |
Additional documents |
![]() ![]() |