Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 1632 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Emission free electricity generation at Harihar, Karnataka |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to further explain why: (a) the equity IRR is calculated for each project owner and not for each site; (b) four spreadsheets are provided for the equity IRR calculations; and (c) CL-2 was closed as the justification given (financial expert of the validation team revised them) is not clear. 2. The DOE is requested to further explain: (a) the assumed PLF of 21.5% as applicable for each site; (b) the reactive power costs of 5% of generation and (c) miscelaneous and other overheads / expenses of 5% of revenue. In doing so, refer to VVM paragraph 111.c. 3. The PP/DOE are requested to explain how the import and transmission losses will be monitored as the project activity consists of 11 wind turbines. A monitoring plan should be applied for each site. |
|
Date | 10 Dec 09 |