10:49 29 Apr 25
Project:
1400 Jinggangshan 36 MW Hydropower Project
- Issuance Request
Project | 1400: Jinggangshan 36 MW Hydropower Project |
---|---|
ISSUANCE STATUS | Issued (on 04 Aug 11) |
Monitoring period | 27 Oct 08 - 25 Mar 10 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
61,086
Serial Range:
Block start: CN-5-387770214-1-1-0-1400
Block end: CN-5-387831299-1-1-0-1400
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: