09:26 02 Aug 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Biomass based renewable energy project in a Solvent Extraction Plant, India (1221) |
---|---|
DOE that requested for issuance and date of request | TUV RHEIN (27 May 11) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
It was reported, on Section A.1 from the monitoring report, that Phase II of the project was implemented to supply both steam and electricity requirements of the plant. However, no explanations were provided on how the electricity requirement from the power plant was met before the implementation of the turbine and for some periods (for example, from 13/08/2009-29/08/2009, 17/09/2009-19/10/2009, among other periods) after it was commissioned. The DOE is required to clarify how it verified the monitoring and calculation of potential project emissions due to the consumption of energy to operate the boilers before and during some periods after the commissioning of the turbine. | |
Date | 02 Aug 11 |