CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Rialma Companhia Energética S/A. – Santa Edwiges II Small Hydro Power Plant – Small Scale CDM Project. (0831) |
---|---|
DOE that requested for issuance and date of request | TÜV NORD (25 Nov 09) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
OTHER ISSUES:
The PP/DOE is required to incorporate the updated calibration dates of the meters located at the power plant, as table "Meters Description" on Pg 6 of the monitoring report was not updated with the information sent by the PP to the DOE in order to close CAR Q1. |
|
Date | 12 Feb 10 |