06:48 09 Nov 24
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | The Godavari Sugar Mills Ltd (TGSML)’s 24 MW Bagasse Based Co-generation Power Project at Sameerwadi (0577) |
---|---|
DOE that requested for issuance and date of request | SGS (11 Aug 09) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
OTHER ISSUES:
1. The DOE shall clearly state the implementation status of the project in each phase, in particular, clarification shall be provided on the status of the second set of steam generators and turbo generator of 30 MW which was proposed to be installed in 2007-2008. 2. Clarifications are required on: a) the role of parameters (e.g. Qproejct plant, y, and energy efficiency of the boiler that would be used in the absence of the project activity) related to heat generation in page 14 of the Verification Report; b) how the PP/DOE carried out the annual energy balance as required by the methodology; c) the function of each of the listed energy meters in Appendix 5 of the Monitoring Report and Verification Report (p.18-19); d) how the NCV (biomass) measurement was carried out, as the verification report (p.8) states that NCV were monitored by the plant site while under the same section is also states that NCV of biomass has been measured annually at reputed laboratories (external agency). |
|
Date | 26 Oct 09 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: