20:57 25 Apr 24
Project:
0427 Electricity generation at 8 MW captive power plant using enthalpy of flue gases from blast furnace operations of Kalyani Steels Limited, in Karnataka state of India.
- Issuance Request
Project | 0427: Electricity generation at 8 MW captive power plant using enthalpy of flue gases from blast furnace operations of Kalyani Steels Limited, in Karnataka state of India. |
---|---|
ISSUANCE STATUS | Issued (on 02 Apr 07) |
Monitoring period | 01 Jan 06 - 31 Dec 06 |
Monitoring report | Monitoring report (115 KB) |
Request for issuance | Signed form (269 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
69,394
Serial Range:
Block start: IN-5-17952814-1-1-0-427
Block end: IN-5-18022207-1-1-0-427
|
Verification and certification reports |
Certification report (192 KB)
Verification report (192 KB) |
Additional documents |
Revised monitoring report (142 KB)
CER calculation sheet (300 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: