Project:
8932 San Pedro Wind Farm Project
- Issuance Request
| Project | 8932: San Pedro Wind Farm Project |
|---|---|
| ISSUANCE STATUS | Issued (on 24 Dec 21) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 20 - 31 Dec 20 |
| Monitoring report |
Monitoring report (506 KB)
|
| Request for issuance |
Signed form (64 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
74,474
Serial Range:
Block start: CL-5-36250832-2-2-0-8932
Block end: CL-5-36325305-2-2-0-8932
|
| Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (431 KB)
Verification report (431 KB)
|
| Additional documents |
Untitled (uploaded 01 Oct 21 19:58:53) (300 KB)
Untitled (uploaded 01 Oct 21 19:58:54) (273 KB)
|

Monitoring report
Untitled (uploaded 01 Oct 21 19:58:54)