21:00 26 Apr 24
Project:
3027 Jiangsu Xiangshui 201MW Wind Power Project
- Issuance Request
Project | 3027: Jiangsu Xiangshui 201MW Wind Power Project |
---|---|
ISSUANCE STATUS | Issued (on 07 Apr 15) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 30 Nov 14 |
Monitoring report | Monitoring report (300 KB) |
Request for issuance | Signed form (165 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
595,572
Serial Range:
Block start: CN-5-914624743-2-2-0-3027
Block end: CN-5-915220314-2-2-0-3027
|
Verification and certification reports |
VVS/VVM version:
VVS 7.0
Certification report (222 KB) Verification report (1114 KB) |
Additional documents |
Xiangshui -ER-7th (63 KB)
Xiangshui -MR-7th (303 KB) |
Offset now: visit the United Nations Carbon Offset Platform