Project: 8242 CTR Rosario Landfill Gas Project - Request for post-registration changes
Project 8242 CTR Rosario Landfill Gas Project
PRC ref PRC-8242-002
Process track Issuance
DOE KBS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 03 Mar 2020 - 31 Dec 2020
Assessment opinion Assessment opinion (331 KB)
Revised PDD  
Supplementary documents Appendix 1 - 3rd Verification_ROSA¦üRIO DEVIATION Spreadsheet v2.xlsx (106 KB)
Signed form Signed form (149 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 23 Sep 21 - Approved
Effective approval date: 23 Sep 21
Historic statuses 25 Aug 21 - Request published