03:06 11 Jan 25
Project:
0928 Methane recovery and effective use of power generation project Norte III-B Landfill.
- Request for post-registration changes
Project | 0928 Methane recovery and effective use of power generation project Norte III-B Landfill. |
---|---|
PRC ref | PRC-0928-002 |
Process track | Issuance |
DOE | SGS |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
|
Applicable crediting period | 01 Jan 08 - 31 Dec 17 |
Assessment opinion | Assessment opinion (1100 KB) |
Revised PDD | Revised PDD (1426 KB) Revised PDD - track changes (1455 KB) |
Supplementary documents | |
Signed form | Signed form (1605 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 21 Jan 13 -
Approved
Effective approval date: 21 Jan 13
|
Historic statuses |
21 Dec 12 -
Request published |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: