Project: 1506 Proactiva Tijuquinhas Landfill Gas Capture and Flaring project - Request for post-registration changes
Project 1506 Proactiva Tijuquinhas Landfill Gas Capture and Flaring project
PRC ref PRC-1506-001
Process track Prior approval
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Sep 2010 - 07 Jan 2012
Assessment opinion Assessment opinion (115 KB)
Revised PDD  
Supplementary documents Appendix 1 - Impact of Deviation on Project Emissions Reductions.xls (25 KB)
Appendix 2 - ER-Second Monitoring Period_Version 1 (before deviation).xls (217 KB)
Appendix 3 - ER-Second Monitoring Period_Version 2 (after deviation).xls (218 KB)
Appendix 4 - ER-Third Monitoring Period_Version 1 (before deviation).xls (239 KB)
Appendix 5 - ER-Third Monitoring Period_Version 2 (after deviation).xls (240 KB)
Appendix 6 - ER-Fourth Monitoring Period_Version 1 (before deviation).xls (134 KB)
Appendix 7 - ER-Fourth Monitoring Period_Version 2 (after deviation).xls (135 KB)
Appendix 8 - PP answer to EB Review_Tijuquinhas.pdf (293 KB)
Signed form Signed form (46 KB)
DOE clarification
VVS version VVS 2.0
Current status 28 Aug 12 - Approved
Effective approval date: 29 Aug 12
Historic statuses 24 Jul 12 - Published
24 Jul 12 - Summary note being prepared
07 Aug 12 - Awaiting EB decision