Project:
0772 Waste Heat based 10 MW captive power project “GPIL- WHRB 2” CDM PROJECT ACTIVITY
- Request for post-registration changes
Project | 0772 Waste Heat based 10 MW captive power project “GPIL- WHRB 2” CDM PROJECT ACTIVITY |
---|---|
PRC ref | PRC-0772-001 |
Process track | Issuance |
DOE | KBS |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Changes to the project or programme design
|
Applicable crediting period | 18 Feb 07 - 17 Feb 17 |
Assessment opinion | Assessment opinion (558 KB) |
Revised PDD | Revised PDD (555 KB) Revised PDD - track changes (566 KB) |
Supplementary documents |
Appendix 1 - Investment Analysis Sheet_revised.xls (230 KB)
Appendix 2 - Levelized Cost Sheet.xlsx (9640 bytes) Appendix 3 - PLF Calculation Sheet.xlsx (11 KB) Appendix 4 - ER Estimation sheet_revised.xls (27 KB) Appendix 5 - DoE Response to UNCCC Clarification.pdf (41 KB) Appendix 6 - PLF & CUF Calculation Sheet.xlsx (16 KB) |
Signed form | Signed form (320 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 19 Dec 14 -
Approved
Effective approval date: 19 Dec 14
|
Historic statuses |
20 Nov 14 -
Request published |