22:25 24 Oct 25
Project:
2661 Univanich TOPI Biogas Project
- Request for post-registration changes
| Project | 2661 Univanich TOPI Biogas Project |
|---|---|
| PRC ref | PRC-2661-001 |
| Process track | Prior approval |
| DOE | SIRIM |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
| Applicable crediting period | 01 Oct 09 - 30 Sep 16 |
| Assessment opinion |
Assessment opinion (244 KB)
|
| Revised PDD |
Revised PDD (2789 KB)
Revised PDD - track changes (2797 KB)
|
| Supplementary documents |
Appendix 1 - 4_Univanich TOPI ER Calcs Revised 2013 v2.xls (311 KB)
|
| Signed form |
Signed form (410 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 20 Feb 14 -
Approved
Effective approval date: 18 Feb 14
|
| Historic statuses |
14 Jan 14 -
Published 14 Jan 14 - Summary note being prepared 28 Jan 14 - Awaiting EB decision |

Assessment opinion
Appendix 1 - 4_Univanich TOPI ER Calcs Revised 2013 v2.xls
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: