Project: 3570 Alto Tuluá Minor Hydroelectric Power Plant - Request for post-registration changes
Project 3570 Alto Tuluá Minor Hydroelectric Power Plant
PRC ref PRC-3570-001
Process track Issuance
DOE Earthood
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Jan 2012 - 27 Jan 2012

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 01 Jan 12 - 31 Dec 18
Assessment opinion Assessment opinion (259 KB)
Revised PDD Revised PDD (1780 KB)   Revised PDD - track changes (1619 KB)
Supplementary documents
Signed form Signed form (117 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 20 Aug 19 - Approved
Effective approval date: 20 Aug 19
Historic statuses 22 Jul 19 - Request published