Project: 6447 Zhejiang Tangcun 32MW Hydropower Project - Request for post-registration changes
Project 6447 Zhejiang Tangcun 32MW Hydropower Project
PRC ref PRC-6447-002
Process track Issuance
DOE RINA
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 27 Apr 2014 - 31 Dec 2014

Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 20 Jun 12 - 19 Jun 19
Assessment opinion Assessment opinion (818 KB)
Revised PDD Revised PDD (686 KB)   Revised PDD - track changes (700 KB)
Supplementary documents
Signed form Signed form (109 KB)
DOE clarification
VVS version VVS 9.0
Current status 03 Jul 15 - Approved
Effective approval date: 03 Jul 15
Historic statuses 04 Jun 15 - Request published