Project: 10573 250 MW Solar Power Plant in Pavagada Solar Park in Karnataka - Request for post-registration changes
Project 10573 250 MW Solar Power Plant in Pavagada Solar Park in Karnataka
PRC ref PRC-10573-001
Process track Issuance
DOE TÜV SÜD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard?
Applicable crediting period 11 Sep 20 - 10 Sep 27
Assessment opinion Assessment opinion (376 KB)
Revised PDD Revised PDD (1630 KB)   Revised PDD - track changes (1602 KB)
Supplementary documents
Signed form Signed form (451 KB)
DOE clarification
VVS version VVS-PA 3.0
Current status 23 Jun 22 - Approved
Effective approval date: 23 Jun 22
Historic statuses 25 May 22 - Request published