20:21 02 Nov 25
Project:
3267 Fujian Longyan Tingzhou Hydropower Station Project
- Request for post-registration changes
| Project | 3267 Fujian Longyan Tingzhou Hydropower Station Project |
|---|---|
| PRC ref | PRC-3267-001 |
| Process track | Issuance |
| DOE | BVI |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Corrections that do not affect project design
|
| Applicable crediting period | 14 Dec 10 - 13 Dec 17 |
| Assessment opinion |
Assessment opinion (218 KB)
|
| Revised PDD |
Revised PDD (1225 KB)
Revised PDD - track changes (1226 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (369 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 07 Jan 13 -
Approved
Effective approval date: 07 Jan 13
|
| Historic statuses |
07 Dec 12 -
Request published |

Assessment opinion
Offset now: visit the United Nations Carbon Offset Platform