Project:
0052 Salvador da Bahia Landfill Gas Management Project
- Request for post-registration changes
| Project | 0052 Salvador da Bahia Landfill Gas Management Project |
|---|---|
| PRC ref | PRC-0052-005 |
| Process track | Prior approval |
| DOE | EPIC |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
| Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
| Applicable crediting period | 01 Jan 11 - 31 Dec 17 |
| Assessment opinion |
Assessment opinion (1706 KB)
|
| Revised PDD |
Revised PDD (4505 KB)
Revised PDD - track changes (5312 KB)
|
| Supplementary documents |
Appendix 1 - 4 Nov 2018_Financial BAT - V.14.1 - 02.11.2018.xlsx (199 KB)
Appendix 2 - 4 Nov 2018_CER BAT - V 14.1 - 02.11.2018.xlsx (997 KB)
|
| Signed form |
Signed form (160 KB)
|
| DOE clarification |
DOE clarification 1 - 4 Nov 2018_PRC Report Salvador LFG Project - 03.11.2018.pdf (1706 KB)
|
| VVS version | VVS-PA 1.0 |
| Current status | 07 Dec 18 -
Approved
Effective approval date: 06 Dec 18
|
| Historic statuses |
22 Oct 18 -
Published 02 Nov 18 - Awaiting DOE clarifications 04 Nov 18 - DOE clarifications received 04 Nov 18 - Summary note being prepared 16 Nov 18 - Awaiting EB decision |

Assessment opinion
Appendix 1 - 4 Nov 2018_Financial BAT - V.14.1 - 02.11.2018.xlsx
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: