02:44 12 Nov 25
Project:
3790 Quanzhou Liupu Hydropower Project
- Request for post-registration changes
| Project | 3790 Quanzhou Liupu Hydropower Project |
|---|---|
| PRC ref | PRC-3790-001 |
| Process track | Issuance |
| DOE | DNV |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 12 Sep 11 - 11 Sep 18 |
| Assessment opinion |
Assessment opinion (101 KB)
|
| Revised PDD |
Revised PDD (1192 KB)
Revised PDD - track changes (747 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (161 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 07 Jan 13 -
Approved
Effective approval date: 07 Jan 13
|
| Historic statuses |
07 Dec 12 -
Request published |

Assessment opinion
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: