Project: 0490 Catalytic N2O destruction project in the tail gas of the Nitric Acid Plant of Abu Qir Fertilizer Co. - Request for post-registration changes
Project 0490 Catalytic N2O destruction project in the tail gas of the Nitric Acid Plant of Abu Qir Fertilizer Co.
PRC ref PRC-0490-001
Process track Prior approval
DOE DNV
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 15 Sep 2013 - 31 Oct 2014
Assessment opinion Assessment opinion (193 KB)
Revised PDD  
Supplementary documents Appendix 1 - 20140311_Temporary Deviation Overview_v1.2_PUBLIC.pdf (264 KB)
Appendix 2 - 20140424_Temporary Deviation Annex_PUBLIC.pdf (306 KB)
Signed form Signed form (152 KB)
DOE clarification
VVS version VVS 2.0
Current status 19 Aug 14 - Approved
Effective approval date: 19 Aug 14
Historic statuses 28 May 14 - Published
11 Jun 14 - Awaiting DOE clarifications
23 Jun 14 - DOE clarifications received
23 Jun 14 - Summary note being prepared
29 Jul 14 - Awaiting EB decision