16:51 12 Dec 24
Project:
1578 Uganda Nile Basin Reforestation Project No.3
- Request for post-registration changes
Project | 1578 Uganda Nile Basin Reforestation Project No.3 |
---|---|
PRC ref | PRC-1578-001 |
Process track | Issuance |
DOE | TÜV SÜD |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Changes specific to A/R project activities
Changes to the project or programme design
|
Applicable crediting period | 01 Apr 07 - 31 Mar 27 |
Assessment opinion | Assessment opinion (1865 KB) |
Revised PDD | Revised PDD (2018 KB) |
Supplementary documents | |
Signed form | Signed form (271 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 26 Aug 13 -
Approved
Effective approval date: 26 Aug 13
|
Historic statuses |
28 Jul 13 -
Request published |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: