Project: 1578 Uganda Nile Basin Reforestation Project No.3 - Request for post-registration changes
Project 1578 Uganda Nile Basin Reforestation Project No.3
PRC ref PRC-1578-001
Process track Issuance
DOE TÜV SÜD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Changes specific to A/R project activities
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 01 Apr 07 - 31 Mar 27
Assessment opinion Assessment opinion (1865 KB)
Revised PDD Revised PDD (2018 KB)  
Supplementary documents
Signed form Signed form (271 KB)
DOE clarification
VVS version VVS 2.0
Current status 26 Aug 13 - Approved
Effective approval date: 26 Aug 13
Historic statuses 28 Jul 13 - Request published