Project: 7093 Los Cocos Wind Farm Project - Request for post-registration changes
Project 7093 Los Cocos Wind Farm Project
PRC ref PRC-7093-002
Process track Prior approval
DOE ICONTEC
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 01 Jan 13 - 31 Dec 19
Assessment opinion Assessment opinion (509 KB)
Revised PDD Revised PDD (2594 KB)   Revised PDD - track changes (2807 KB)
Supplementary documents
Signed form Signed form (227 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 25 Sep 19 - Approved
Effective approval date: 23 Sep 19
Historic statuses 19 Aug 19 - Published
19 Aug 19 - Summary note being prepared
03 Sep 19 - Awaiting EB decision