10:22 05 Jul 25
Project:
2021 Shandong Haiyang Qiuershan Wind Power Project
- Request for post-registration changes
Project | 2021 Shandong Haiyang Qiuershan Wind Power Project |
---|---|
PRC ref | PRC-2021-001 |
Process track | Prior approval |
DOE | RINA |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
Applicable crediting period | 08 Feb 09 - 07 Feb 16 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents | |
Signed form |
![]() |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 27 Aug 13 -
Approved
Effective approval date: 22 Aug 13
|
Historic statuses |
16 Jul 13 -
Published 16 Jul 13 - Summary note being prepared 02 Aug 13 - Awaiting EB decision |