Project: 2151 Yunnan Leidatan 108MW Hydropower Project - Request for post-registration changes
Project 2151 Yunnan Leidatan 108MW Hydropower Project
PRC ref PRC-2151-001
Process track Issuance
DOE BVI
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 09 Feb 09 - 08 Feb 16
Assessment opinion Assessment opinion (145 KB)
Revised PDD Revised PDD (634 KB)   Revised PDD - track changes (635 KB)
Supplementary documents
Signed form Signed form (1785 KB)
DOE clarification
VVS version VVS 2.0
Current status 15 Apr 13 - Approved
Effective approval date: 15 Apr 13
Historic statuses 15 Mar 13 - Request published