Project: 2185 Methane Capture and On-site Power Generation Project at Sungai Kerang Palm Oil Mill in Sitiawan, Perak, Malaysia - Request for post-registration changes
Project 2185 Methane Capture and On-site Power Generation Project at Sungai Kerang Palm Oil Mill in Sitiawan, Perak, Malaysia
PRC ref PRC-2185-001
Process track Prior approval
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No
Applicable crediting period 01 Jun 09 - 31 May 19
Assessment opinion Assessment opinion (709 KB)
Revised PDD Revised PDD (1154 KB)   Revised PDD - track changes (1202 KB)
Supplementary documents Appendix 1 - 2185 CashFlow.xls (247 KB)
Signed form Signed form (53 KB)
DOE clarification
VVS version VVS 2.0
Current status 27 Sep 13 - Approved
Effective approval date: 27 Sep 13
Historic statuses 20 Aug 13 - Published
20 Aug 13 - Summary note being prepared
06 Sep 13 - Awaiting EB decision