Project: 1079 Gansu Diebu Duoer 32MW Hydropower Project - Request for post-registration changes
Project 1079 Gansu Diebu Duoer 32MW Hydropower Project
PRC ref PRC-1079-001
Process track Issuance
DOE CCSC
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 08 Jul 07 - 07 Jul 14
Assessment opinion Assessment opinion (407 KB)
Revised PDD Revised PDD (1001 KB)   Revised PDD - track changes (1018 KB)
Supplementary documents
Signed form Signed form (168 KB)
DOE clarification
VVS version VVS 2.0
Current status 05 Feb 16 - Approved
Effective approval date: 05 Feb 16
Historic statuses 07 Jan 16 - Request published