16:44 17 May 25
Project:
2687 Pakarab Fertiliser Co-generation Power Project
- Request for post-registration changes
Project | 2687 Pakarab Fertiliser Co-generation Power Project |
---|---|
PRC ref | PRC-2687-001 |
Process track | Prior approval |
DOE | DNV |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
Applicable crediting period | 21 Dec 09 - 20 Dec 16 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents |
![]() ![]() ![]() Appendix 4 - Gas Chromatograph Specifications.jpg (286 KB) ![]() |
Signed form |
![]() |
DOE clarification |
![]() |
VVS version | VVS 2.0 |
Current status | 20 Sep 12 -
Approved
Effective approval date: 29 Aug 12
|
Historic statuses |
19 Jun 12 -
Published 26 Jul 12 - Awaiting DOE clarifications 08 Aug 12 - DOE clarifications received 08 Aug 12 - Summary note being prepared 09 Aug 12 - Awaiting EB decision |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: