07:23 08 May 25
Project:
0581 MAHARASHTRA, INDIA- Kurkumbh, 1.5 MW Biomass / Bagasse Based Co-generation Power Project
- Request for post-registration changes
Project | 0581 MAHARASHTRA, INDIA- Kurkumbh, 1.5 MW Biomass / Bagasse Based Co-generation Power Project |
---|---|
PRC ref | PRC-0581-001 |
Process track | Prior approval |
DOE | TÜV NORD |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
Applicable crediting period | 01 Jan 06 - 31 Dec 15 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents | |
Signed form |
![]() |
DOE clarification |
|
VVS version | VVS 2.0 |
Current status | 08 Feb 13 -
Approved
Effective approval date: 07 Feb 13
|
Historic statuses |
11 Dec 12 -
Published 25 Dec 12 - Awaiting DOE clarifications 08 Jan 13 - DOE clarifications received 08 Jan 13 - Summary note being prepared 17 Jan 13 - Awaiting EB decision |