Project: 2853 Huade Daditaihong 49.5MW Wind Power Project - Request for post-registration changes
Project 2853 Huade Daditaihong 49.5MW Wind Power Project
PRC ref PRC-2853-001
Process track Prior approval
DOE BVI
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No
Applicable crediting period 12 Feb 10 - 11 Feb 17
Assessment opinion Assessment opinion (504 KB)
Revised PDD Revised PDD (1317 KB)   Revised PDD - track changes (1385 KB)
Supplementary documents
Signed form Signed form (53 KB)
DOE clarification
VVS version VVS 2.0
Current status 23 Oct 12 - Approved
Effective approval date: 23 Oct 12
Historic statuses 18 Sep 12 - Published
18 Sep 12 - Summary note being prepared
02 Oct 12 - Awaiting EB decision