Project: 4205 Sichuan Maoergai Hydropower Project - Request for post-registration changes
Project 4205 Sichuan Maoergai Hydropower Project
PRC ref PRC-4205-001
Process track Prior approval
DOE TUV RHEIN
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 21 Oct 11 - 20 Oct 18
Assessment opinion Assessment opinion (350 KB)
Revised PDD Revised PDD (840 KB)   Revised PDD - track changes (680 KB)
Supplementary documents Appendix 1 - IRR_ver03.xls (1061 KB)
Appendix 2 - Maoergai PDD - VVS Version_Registration - clean.pdf (531 KB)
Signed form Signed form (91 KB)
DOE clarification
VVS version VVS 2.0
Current status 26 Feb 14 - Approved
Effective approval date: 25 Feb 14
Historic statuses 21 Jan 14 - Published
21 Jan 14 - Summary note being prepared
04 Feb 14 - Awaiting EB decision