Project: 7369 Wind Power Project in Gujarat, India - Request for post-registration changes
Project 7369 Wind Power Project in Gujarat, India
PRC ref PRC-7369-001
Process track Issuance
DOE DNV
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 05 Oct 12 - 04 Oct 22
Assessment opinion Assessment opinion (185 KB)
Revised PDD Revised PDD (1062 KB)   Revised PDD - track changes (1053 KB)
Supplementary documents Appendix 1 - ISS-INVEST-ANALY-7369-28-08.xlsx (44 KB)
Signed form Signed form (202 KB)
DOE clarification
VVS version VVS 2.0
Current status 18 Nov 13 - Approved
Effective approval date: 18 Nov 13
Historic statuses 18 Oct 13 - Request published