Project: 4775 CECIC Taiyangshan Grid-connected Solar PV Power Generation Phase 1 Project - Request for post-registration changes
Project 4775 CECIC Taiyangshan Grid-connected Solar PV Power Generation Phase 1 Project
PRC ref PRC-4775-002
Process track Issuance
DOE BVI
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 10 Jun 11 - 09 Jun 18
Assessment opinion Assessment opinion (213 KB)
Revised PDD Revised PDD (780 KB)   Revised PDD - track changes (696 KB)
Supplementary documents
Signed form Signed form (1309 KB)
DOE clarification
VVS version VVS 2.0
Current status 22 Aug 13 - Approved
Effective approval date: 22 Aug 13
Historic statuses 24 Jul 13 - Request published