Project: 3364 Xiangcheng County Maxionggou Hydropower Project - Request for post-registration changes
Project 3364 Xiangcheng County Maxionggou Hydropower Project
PRC ref PRC-3364-001
Process track Issuance
DOE TUV RHEIN
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 20 Nov 10 - 19 Nov 17
Assessment opinion Assessment opinion (902 KB)
Revised PDD Revised PDD (384 KB)   Revised PDD - track changes (389 KB)
Supplementary documents
Signed form Signed form (91 KB)
DOE clarification
VVS version VVS 2.0
Current status 11 Apr 13 - Approved
Effective approval date: 11 Apr 13
Historic statuses 13 Mar 13 - Request published