Project: 4118 Asahan 1 Hydroelectric Power Plant 2 x 90 MW - Request for post-registration changes
Project 4118 Asahan 1 Hydroelectric Power Plant 2 x 90 MW
PRC ref PRC-4118-001
Process track Issuance
DOE DNV
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 01 Mar 11 - 28 Feb 18
Assessment opinion Assessment opinion (113 KB)
Revised PDD Revised PDD (889 KB)   Revised PDD - track changes (850 KB)
Supplementary documents
Signed form Signed form (212 KB)
DOE clarification
VVS version VVS 2.0
Current status 21 Nov 12 - Request published