Project:
2148 Chumporn applied biogas technology for advanced waste water management
- Request for post-registration changes
Project | 2148 Chumporn applied biogas technology for advanced waste water management |
---|---|
PRC ref | PRC-2148-001 |
Process track | Prior approval |
DOE | GLC |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 09 Feb 09 - 08 Feb 19 |
Assessment opinion | Assessment opinion (229 KB) |
Revised PDD | Revised PDD (1565 KB) Revised PDD - track changes (1720 KB) |
Supplementary documents |
Appendix 1 - CPI_Revised ER calculation sheet for ex-ante estimation_2014-08-09.xls (241 KB)
Appendix 2 - CPI_Revised IRR calculation_2014-11-20.xls (347 KB) |
Signed form | Signed form (449 KB) |
DOE clarification |
DOE clarification 1 - Response to Clarification_2014-11-24.pdf (45 KB)
|
VVS version | VVS 2.0 |
Current status | 29 Dec 14 -
Approved
Effective approval date: 28 Dec 14
|
Historic statuses |
28 Oct 14 -
Published 12 Nov 14 - Awaiting DOE clarifications 24 Nov 14 - DOE clarifications received 24 Nov 14 - Summary note being prepared 08 Dec 14 - Awaiting EB decision |