00:34 12 Nov 25
Project:
3991 Gu’ertu River Stage VI and VII 17MW Bundled Hydropower Project
- Request for post-registration changes
| Project | 3991 Gu’ertu River Stage VI and VII 17MW Bundled Hydropower Project |
|---|---|
| PRC ref | PRC-3991-001 |
| Process track | Prior approval |
| DOE | TUV RHEIN |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
| Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 14 Jan 11 - 13 Jan 18 |
| Assessment opinion | Assessment opinion (505 KB) |
| Revised PDD |
Revised PDD (480 KB)
Revised PDD - track changes (579 KB)
|
| Supplementary documents |
Appendix 1 - Calculation process of Transmission line loss and transformer loss.pdf (1478 KB)
Appendix 2 - Meeting records for Guertu 6&7 monitoring issues.pdf (937 KB)
|
| Signed form | Signed form (944 KB) |
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 21 Nov 12 -
Approved
Effective approval date: 21 Nov 12
|
| Historic statuses |
17 Oct 12 -
Published 17 Oct 12 - Summary note being prepared 31 Oct 12 - Awaiting EB decision |

Revised PDD